We would like to inform you of the tentative dates for the upcoming GovCMS Drupal 10 (D10) release and deployment.

The final release date is subject to change, as it will be determined by the testing outcomes. The date will be confirmed when the distribution is released and the release notes are expected to be sent on Monday 15 April 2024 .

As a reminder, a SaaS deployment block is in place ONLY while we update the production branches. During this time, you will still be able to develop and deploy to non-production feature branches. We are wanting to give you as much lead time as possible, should you need to adjust your timeframes.

PaaS deployments schedules are not impacted.

Tentative deployment schedule:
- Deployment to commence from 6am Tuesday 16 April 2024 and will be conducted throughout the daytime.
- Production branches completed by 10am Wednesday 17 April 2024
- Non-Production branches completed by 10am Thursday 18 April 2024


If you have any concerns, raise a ticket at https://www.govcms.support
Posted Apr 02, 2024 - 16:30 AEDT